Step | Step name | Tasks | Next Step | Who | Person | Duration |
---|---|---|---|---|---|---|
INITIATION | ||||||
P10 | Submit request |
| P20 | Project Holder | 10 min | |
P20 | Registration of request |
| P30 | ExSec | Samuel | 10 min |
P30 | Check Eligibility |
| P40,P70 | ExSec | Samuel | 20 min |
P40 | Check login of Project Owner and contact person |
| P40 | ExSec | Marc | 20 min |
P50 | Create project folder |
| P60 | ExSec | Samuel | 60 min |
P60 | Send notification of admission |
| P80 | ExSec | Samuel | 15 min |
P70 | Send rejection notice |
| P320 | ExSec | Samuel, Paul | 10 min |
P80 | Provide project information |
| P90 | Project Owner | ||
P90 | Formality check |
| P80,P100 | ExSec | Samuel | 20 min |
P100 | Identify an FAPI Assessor |
| P110 | ExSec and STC | Elena | 20 min |
P110 | Check login of Assessor |
| P120 | ExSec | Marc | 10 min |
P120 | Configure system for the Assessor |
| P130 | ExSec | Samuel | 20 min |
Step | Step name | STEP 1 - SAFEGUARD CRITERIA | Next step | Who | Person | Duration |
P130 | Assess compliance with safeguard criteria |
| P140, P160 | Assessor | 60 min | |
P140 | Make improvements to meet safeguard criteria |
| P150 | Project Owner | ||
P150 | Reassessment of safeguard criteria |
| P320, P160 | Assessor | 60 min | |
Step | Step name | STEP 2 - DIRECT CRITERIA | Next step | Who | Person | Duration |
P160 | Assess compliance with direct criteria |
| P170, P190 | Assessor | 120 min | |
P170 | Make improvements to meet direct criteria |
| P180 | Project Owner | ||
P180 | Reassessment of direct criteria |
| P320, P190 | Assessor | 120 min | |
Step | Step name | STEP 3 - INDIRECT CRITERIA | Next step | Who | Person | Duration |
P190 | Assess compliance with indirect criteria |
| P200, P220 | Assessor | 60 min | |
P200 | Make improvements to meet indirect criteria |
| P210 | Project Owner | ||
P210 | Reassessment of indirect criteria |
| P320, P220 | Assessor | 60 min | |
Step | Step name | STEP 4 - CROSS-CUTTING |
|
|
|
|
P220 | Assess compliance with cross-cutting criteria |
| P230, P250 | Assessor | 60 min | |
P230 | Make improvements to meet indirect criteria |
| P240 | Project Owner | ||
P240 | Reassessment of cross-cutting criteria |
| P320,P250 | Assessor | 60 min | |
Step | Step name | CONCLUSION | Next step | Who | Person | Duration |
P250 | Elaborate assessment summary report |
| P260 | Assessor | 60 min | |
P260 | Validation of the assessment summary report by the STC |
| P270,P280 | STC | Elena | 30 min |
P270 | Improve the summary report |
| P260 | Assessor | 30 min | |
P280 | Validation of the assessment summary report by ExSec |
| P260,P290 | ExSec | Paul | 30 min |
P290 | Notify Project Owner |
| P300 | ExSec | Paul | 30 min |
P300 | Publish project summary on 4p1000.org |
| P310 | ExSec | Samuel | |
P310 | Publish project summary in investment opportunities |
| P330 | ExSec | Samuel | |
P320 | Terminate assessment |
| P330 | ExSec | Samuel | |
P330 | End | ExSec |